Multiple Choice
If the standard quantity of materials is 84,500 units at $0.15 per unit and the actual quantity is 95,000 units at $0.12 per unit,then the journal entry to record the cost of materials used includes:
A) A debit to Work in Process Inventory of $11,400.
B) A debit to Work in Process Inventory of $12,675.
C) A debit to Materials Price variance of $2,850.
D) A credit to Materials Price variance of $1,575.
Correct Answer:

Verified
Correct Answer:
Verified
Q80: Favorable standard cost variances are normally closed
Q81: The calculation of the labor rate variance
Q82: [The following information applies to the questions
Q83: Which statement is true regarding a standard
Q84: If the actual cost per pound of
Q86: Excessive overtime hours worked by direct labor
Q87: Standard cost system overhead variances<br>Rogers Manufacturing produces
Q88: Standard cost system materials variances<br>Levron Corporation manufactures
Q89: The use of inexpensive,low quality,materials often results
Q90: In evaluating cost variances,the accounting department determines