Multiple Choice
AFD Production uses a predetermined overhead rate based upon direct labour hours. The firm has the following budgeted and actual data for the current year:
Budgeted factory overhead cost $6000
Actual factory overhead cost $5000
Budgeted direct labour hours 1000
Actual direct labour hours 1100
What was the amount of underapplied or overapplied overhead for the year?
A) $500 overapplied
B) $500 underapplied
C) $1600 underapplied
D) $1600 overapplied
Correct Answer:

Verified
Correct Answer:
Verified
Q56: Equivalent units of production measures:<br>A) the number
Q57: Something that is not a feature of
Q58: Which account would be adjusted for the
Q59: Magenta Ltd uses a job order costing
Q60: In an 'ideal' just-in-time processing plant, the
Q61: The type of product costing system used
Q62: Which best describes the set of costs
Q64: It is incorrect concerning Activity-Based Costing [ABC]
Q65: Dreamtime Manufacturing uses the weighted-average method of
Q66: Beginning balance Job No. 58 $20 000<br>Direct