Multiple Choice
Table 9.12
A company with a process layout wants to rearrange its facility in the space available.There are six departments,and the flow among them is given in the following trip matrix.The shape and the size of the space available is also given.Assume rectilinear distances.
Trips Between Departments
Location Positions
-Use the information from Table 9.12.Consideration of safety and EPA regulations restrict the location of certain departments: Department A must be assigned to positions 1 or 4,Department D must be assigned to positions 4 or 6,Department E must be assigned to positions 1 or 3,and Department F must be assigned to positions 3 or 6.What is the least load-distance assignment of the departments to locations?
A)
B)
C)
D)
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Table 9.6<br>Nuts-and-Bolts Inc. wishes to find
Q55: This clustering of competing firms can create
Q56: Automan,Inc.makes "tennis robots" on an assembly line
Q60: Consider the following trip matrix for a
Q61: An advantage of flexible- flow layouts over
Q64: Widgets,Inc.wishes to locate two new manufacturing facilities.Based
Q95: One dominant factor in locating manufacturing facilities
Q122: is the straight- line distance, or shortest
Q172: Secondary location factors are derived from competitive
Q174: Table 9.16<br>Balance the following lines for