Automan,Inc.makes "tennis robots" on an assembly line with 9 tasks.The tasks and their times follow. The desired output rate is 50 robots an hour.The "theoretical maximum efficiency" on the line is
A) less than 85%.
B) more than 85% but less than or equal to 90%.
C) more than 90% but less than or equal to 95%.
D) more than 95%.