Which of the following is NOT one of the five steps involved in planning projects?
A) Analyzing cost-time trade-offs
B) Developing the schedule
C) Diagramming the network
D) Monitoring resource usage during the execution phase
Correct Answer:

Verified
Correct Answer:
Verified