Which one of the following best describes the critical path of a PERT/CPM network?
A) the sequence of activities between a project's start and finish that takes the longest time to complete
B) the sequence of activities between a project's start and finish that has the maximum amount of activity slack
C) the set of activities that has no precedence relationships
D) the sequence of activities that has the lowest normal activity cost
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q15: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q16: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q17: The phase of project management that takes
Q18: Table 7.13<br>All activity times for the project
Q20: Table 7.8<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.8
Q21: Table 7.14<br>You are responsible for managing a
Q22: Consider the activities, durations, and predecessor relationships
Q23: Figure 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 7.1
Q24: Scope creep is one of the primary