Multiple Choice
To calculate the probability of completing a project by a certain date,
A) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
B) the variance of the distribution of project completion times is taken to be one-sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
C) we assume that the activity durations are independent of each other so that the normal distribution can be used.
D) we only need the parameters of the beta distribution for the finish node of the diagram.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Which one of the following best describes
Q28: What characteristics should project manager possess?
Q34: A(n) _ is an interrelated set of
Q55: Risk is a measure of the probability
Q59: Table 3.2<br>Time (days)<br> <span class="ql-formula"
Q63: Table 3.12<br>You are responsible for managing
Q66: What are the benefits of using CPM/PERT?
Q66: Table 3.10<br>You are responsible for managing
Q83: Projects cannot have more than one critical
Q91: When using the beta distribution for estimating