Multiple Choice
Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.12,which of the following activities has the largest amount of slack?
A) Activity C
B) Activity D
C) Activity E
D) Activity H
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Which one of the following best describes
Q27: Activities on the critical path have zero
Q28: What characteristics should project manager possess?
Q34: A(n) _ is an interrelated set of
Q55: Risk is a measure of the probability
Q59: Table 3.2<br>Time (days)<br> <span class="ql-formula"
Q64: To calculate the probability of completing a
Q66: What are the benefits of using CPM/PERT?
Q66: Table 3.10<br>You are responsible for managing
Q91: When using the beta distribution for estimating