Question 63

Multiple Choice

Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks) .
 Activity  Expected  Time  Immediate  Predecessor (s) A3 B 3 C 5 A  D 4 A,B  E 4 B  F 4 C,D  G 3D,EH5 F,G\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 3 & \cdots - \\\text { B } & 3 & - \\\text { C } & 5 & \text { A } \\\text { D } & 4 & \text { A,B } \\\text { E } & 4 & \text { B } \\\text { F } & 4 & \text { C,D } \\\text { G } & 3 & \mathrm { D } , \mathrm { E } \\\mathrm { H } & 5 & \mathrm {~F} , \mathrm { G } \\\hline\end{array}
-Using Table 3.12,which of the following activities has the largest amount of slack?


A) Activity C
B) Activity D
C) Activity E
D) Activity H

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions