Which of the Following Is a Goal of Project Management

Question 134

Multiple Choice

Which of the following is a goal of project management?


A) the project completed one month early while going over budget by less than 5%
B) the project completed under budget and on time with modified specifications
C) the project completed according to specifications,on time and within budget
D) the project completed on time and with improved specifications for a small cost overage

Correct Answer: