Multiple Choice
The term used to describe when decisions are made during the PM process to implement additional functions beyond what was defined in the project scope is called:
A) reengineering
B) process mapping
C) project add-ons
D) project creep
Correct Answer:

Verified
Correct Answer:
Verified