Multiple Choice
A method for analyzing a project that calculates the starting and ending times for each activity, determines which activities are critical to the completion of a project is called:
A) the SDLC
B) a Gantt chart
C) CPM
D) PERT
Correct Answer:

Verified
Correct Answer:
Verified