Multiple Choice
The project management chart that graphically models the sequence of project tasks and their interrelationships using a flowchart diagrams is called a:
A) Gantt chart.
B) PERT chart.
C) work breakdown.
D) project charter.
Correct Answer:

Verified
Correct Answer:
Verified