Multiple Choice
Rite-Bilt Contractors,Inc. ,agrees to build a motel for Slumber Motels Corporation.The project proceeds according to plan,but before it is done,Slumber tells Rite-Bilt to quit.Rite-Bilt may recover
A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.
Correct Answer:

Verified
Correct Answer: