Bob contracts to work for Central Construction Corporation (CCC) during July for $4,500.On June 30,CCC cancels the contract.Bob declines a similar job with Design Builders,Inc. ,which would have paid $4,000.Bob files a suit against CCC.As compensatory damages,Bob can recover


A) $4,500.
B) $4,000.
C) $500.
D) nothing.