menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Management Science Study Set 1
  4. Exam
    Exam 8: Project Management
  5. Question
    The Early Finish for an Activity on the Critical Path
Solved

The Early Finish for an Activity on the Critical Path

Question 100

Question 100

True/False

The early finish for an activity on the critical path is equal to the latest finish of the preceding activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q95: Elements of project planning include<br>A) identifying time-cost

Q96: If the earliest finish for activity C

Q97: The expected project completion time is assumed

Q98: A GANTT chart represents mainly<br>A) an immediate

Q99: Project teams are made up of individuals

Q101: The diagram below shows the activities

Q102: The critical path is the longest path

Q103: A work breakdown structure breaks down a

Q104: Consider the following project.<br> <span

Q105: The critical path activities have no _.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines