    The Early Start of an Activity That Has Only One
Solved

The Early Start of an Activity That Has Only One

Question 68

Question 68

True/False

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q63: The normal cost for an activity is

Q65: A PERT/CPM activity has an optimistic time

Q66: The earliest finish time for the final

Q67: Project control involves<br>A) crashing.<br>B) three time estimates.<br>C)

Q69: The early start for an activity on

Q70: Consider the following project.<br> <span

Q71: Consider the following project.<br> <span

Q72: Refer to the table below to

Q73: The critical path activities have no slack.

Q90: What is the estimated standard deviation (in

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines