Multiple Choice
The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
A) $1000
B) $1250
C) $2000
D) $2500
Correct Answer:

Verified
Correct Answer:
Verified