    If the Early Start for Activity a Is Equal to 23
Solved

If the Early Start for Activity a Is Equal to 23

Question 80

Question 80

Short Answer

If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is the earliest finish for activity A?

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q39: What is the critical path for this

Q75: A _ shows who in the organization

Q77: Consider the following network.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg" alt="Consider

Q78: Joe used a project management software package

Q79: Project crashing is a method for shortening

Q81: Given the following information for a

Q82: Project _ is a method for shortening

Q83: The diagram below shows the activities

Q84: Consider the following network.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg" alt="Consider

Q85: The expected project completion time is assumed

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines