Multiple Choice
Joe used a project management software package and has determined the following results for a given project:
Expected completion time of the project = 22 days
Variance of project completion time = 2.77
What is the probability of completing the project within 20 days?
A) 0.3849
B) 0.8849
C) 0.1151
D) 0.7642
Correct Answer:

Verified
Correct Answer:
Verified
Q39: What is the critical path for this
Q73: The critical path activities have no slack.
Q74: Consider the following project.<br> <span
Q75: A _ shows who in the organization
Q77: Consider the following network.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg" alt="Consider
Q79: Project crashing is a method for shortening
Q80: If the early start for activity A
Q81: Given the following information for a
Q82: Project _ is a method for shortening
Q83: The diagram below shows the activities