Question 18

Multiple Choice

Consider the following project.
 Activity  Immediate  Processor  Activity Time  (days)   A 6 B 8 C  A, B 5 D  B 4 E  C 7 F  C, D 3 G  D 6 H  E, F, G 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Processor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (days) }\end{array} \\\hline \text { A } & - & 6 \\\hline \text { B } & - & 8 \\\hline \text { C } & \text { A, B } & 5 \\\hline \text { D } & \text { B } & 4 \\\hline \text { E } & \text { C } & 7 \\\hline \text { F } & \text { C, D } & 3 \\\hline \text { G } & \text { D } & 6 \\\hline \text { H } & \text { E, F, G } & 5 \\\hline\end{array}
-How much can activity F be delayed without delaying the project completion?


A) 1 day
B) 2 days
C) 3 days
D) 4 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions