Note: This problem requires the use of a linear programming application such as Solver or Analytic Solver.
The university administration would like to add some additional parking locations. To make everyone happy, they would like each building to be within a 5 minute walk of one set of new parking spaces (the spaces will be added in blocks of 10 parking spaces) . The university is considering six locations for the new parking spaces, but would like to minimize the overall cost of the project. In addition to the walking time requirement, the university would like to add at least 40 new parking spaces (at least 4 blocks of 10) . To help with the decision, the management science department formulated the following linear programming model:
Min 400x1 + 375x2 + 425x3 + 350x4 +410x5 + 500x6
s.t. x1 + x2 + x5 + x6 ? 1{Residence Hall A constraint}
X1 + x2 + x3 ? 1 {Residence Hall B constraint}
X4 + x5 + x6 ? 1 {Science building constraint}
X1 + x4 + x5 ? 1 {Music building constraint}
X2 + x3 + x4 ? 1 {Math building constraint}
X3 + x4 + x5 ? 1 {Business building constraint}
X2 + x5 + x6 ? 1 {Auditorium constraint}
X1 + x4 + x6 ? 1 {Arena constraint}
X1 + x2 + x3 + x4 + x5 + x6 ? 4 {Total locations constraint}
Set up the problem in Excel and find the optimal solution. Which locations are selected?
A) Locations 1, 3, 4, and 5
B) Locations 1, 2, 4, and 5
C) Locations 1, 2, 3, and 5
D) Locations 2, 3, 4, and 5
E) Locations 1, 3, and 5
Correct Answer:

Verified
Correct Answer:
Verified
Q22: A BIP problem considers one yes-or-no decision
Q23: A bakery produces both pies and
Q24: A firm has prepared the following
Q25: A firm has prepared the following
Q26: The university administration would like to
Q28: Which of the following techniques or tools
Q29: Binary variables can have the following values:<br>A)
Q30: If activities A and B are mutually
Q31: Binary variables are variables whose only possible
Q32: A firm has prepared the following