Multiple Choice
Once change has been implemented and stabilized, when should re-evaluation of that stabilization occur to make sure the project has been accepted?
A) between 3 months and 1 year after the change
B) between 4 months and 1 year after the change
C) at 5 months or 1 year after the change
D) at 6 months or 1 year after the change
Correct Answer:

Verified
Correct Answer:
Verified