Question 106

Multiple Choice

Because problems with fixed-position layouts are so difficult to solve well onsite, operations managers:


A) virtually never employ this layout strategy.
B) utilize this approach only for construction projects such as bridges and office towers.
C) increase the size of the site.
D) often complete as much of the project as possible off site.
E) utilize this layout only for defense contractors.

Correct Answer: