Multiple Choice
A grill assembly takes 20 washers.Instead of listing these washers separately,they are grouped into a single kit for production.How is the bill of material for the washers classified?
A) "pseudo"
B) planning
C) modular
D) low-level
E) A and B
Correct Answer: