An assumption of PERT is:


A) Activity times are constant.
B) Uncertainty of individual time estimates exists.
C) Distribution of project completion times and probability that each activity is on the critical path can be computed.
D) b and c

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: The project management concept that can be

Q5: Gantt charts are effective if:<br>A)Activities are highly

Q6: The job of the project manager is

Q7: CPM network scheduling assumes a second order

Q7: A forward pass of the above network

Q8: The advantage(s)of the network method over the

Q10: The advantage(s)that Gantt chart has over the

Q11: Which of the following statements about CPM

Q12: "Slack" refers to the difference between:<br>A)Late and

Q13: Controlling a project does NOT entail:<br>A)Monitoring costs,time,and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines