Multiple Choice
Which of the following statements about CPM is true?
A) CPM is an example of a variable time project scheduling method.
B) The CPM method is well suited when activity times are expected to vary a lot.
C) The CPM method is well suited when activity times are fairly constant and can be reduced by spending more money.
D) The CPM method is well suited for R&D projects and for scheduling computer systems.
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q6: The job of the project manager is
Q7: CPM network scheduling assumes a second order
Q7: A forward pass of the above network
Q8: The advantage(s)of the network method over the
Q9: An assumption of PERT is:<br>A)Activity times are
Q10: The advantage(s)that Gantt chart has over the
Q12: "Slack" refers to the difference between:<br>A)Late and
Q13: Controlling a project does NOT entail:<br>A)Monitoring costs,time,and
Q15: Estimating the time required for each task
Q16: Which of the following statements is incorrect