Multiple Choice
If a manufacturer has daily requirements for products A,B and C of 360,100,and 300,respectively,then the daily schedule will call for the following amounts of each product to be produced per cycle:
A) | (36) A (10) B (30) C |
B) | (18) A (5) B (15) C |
C) | (72) A (20) B (60) C |
D) | (18) A (10) B (30) C |
Correct Answer:

Verified
Correct Answer:
Verified