    If a Factory Has 100,000 Units of Raw Materials Waiting
Solved

If a Factory Has 100,000 Units of Raw Materials Waiting

Question 1

Question 1

Multiple Choice

If a factory has 100,000 units of raw materials waiting in the system and if the average flow rate of the system is 5000 units per day,then according to Little's Law,the average throughput time is:


A) 0.5 days
B) 20 days
C) 0.05 days
D) 100 days
E) 10 days

Correct Answer:

verifed

Verified

Related Questions

Q2: Any given process will have at least

Q3: A numerically controlled machining center has an

Q5: Business process reengineering is cross-functional in nature

Q6: If I denotes the average inventory in

Q7: Business process reengineering (BPR)has encountered some implementation

Q8: Which of the following statements about Little's

Q9: Which of the following would not be

Q10: A line of visibility separates the parts

Q10: The average flow rate into a bank

Q11: One step in process flow analysis is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines