Multiple Choice
If a factory has 100,000 units of raw materials waiting in the system and if the average flow rate of the system is 5000 units per day,then according to Little's Law,the average throughput time is:
A) 0.5 days
B) 20 days
C) 0.05 days
D) 100 days
E) 10 days
Correct Answer:

Verified
Correct Answer:
Verified