A project consists of the following four activities with activity times in days:
Table YY
-Using Table YY,the amount of slack associated with activity C is
A) 4 days.
B) 3 days.
C) 2 days.
D) 1 day.
Correct Answer:

Verified
Correct Answer:
Verified