The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table ZZ
-Using Table ZZ,how much slack is associated with activity C?
A) 0 weeks.
B) 4.50 weeks.
C) 12.67 weeks.
D) 31.00 weeks.