Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table ZZ
-Using Table ZZ,the earliest finish time for activity C is
A) 5.00 weeks.
B) 8.17 weeks.
C) 9.50 weeks.
D) 12.67 weeks.
Correct Answer:

Verified
Correct Answer:
Verified