Solved

The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 22

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the earliest finish time for activity C is A) 5.00 weeks. B) 8.17 weeks. C) 9.50 weeks. D) 12.67 weeks. Table ZZ
-Using Table ZZ,the earliest finish time for activity C is


A) 5.00 weeks.
B) 8.17 weeks.
C) 9.50 weeks.
D) 12.67 weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions