Which of the following is not used to calculate probabilistic time estimates?


A) optimistic
B) most likely
C) least likely
D) pessimistic

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q20: The following table of probabilistic time estimates

Q21: A typical project team is cross-functional consisting

Q22: The following table of probabilistic time estimates

Q23: The earliest start time for the first

Q24: A project's duration can be reduced by

Q26: The single most important criterion for the

Q27: A project consists of the following four

Q28: A project consists of the following activities:<br>

Q29: A project consists of the following four

Q30: Project scope,one of the basic elements of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines