Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table ZZ
-Using Table ZZ,the probability that the project could be completed in 34 weeks or less is approximately
A) 86 percent.
B) 89 percent.
C) 91 percent.
D) 96 percent.
Correct Answer:

Verified
Correct Answer:
Verified
Q73: A project consists of the following four
Q74: A dummy variable is an activity inserted
Q75: In project management the term slack refers
Q76: A unique,one-time operational activity or effort is
Q77: The following table of probabilistic time estimates
Q79: Crashing activities with positive slack reduces a
Q80: Briefly discuss project management and what it
Q81: The following table of probabilistic time estimates
Q82: Diversity among project team members brings different<br>A)views.<br>B)experiences.<br>C)values.<br>D)All
Q83: For an activity-on-node (AON)network,<br>A)arrows represent activities and