Multiple Choice
In project management the term slack refers to the amount of time
A) to complete an activity without delaying the project.
B) an activity can be delayed without delaying the project.
C) needed to complete the entire project.
D) required to complete the project's critical activities.
Correct Answer:

Verified
Correct Answer:
Verified