    The Reduction in One or More Activities Normal Time to Shorten
Solved

The Reduction in One or More Activities Normal Time to Shorten

Question 72

Question 72

Multiple Choice

The reduction in one or more activities normal time to shorten the project duration is called


A) crashing.
B) scheduling.
C) adjusting.
D) None of these answer choices is correct.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q67: Control,one of the basic elements of a

Q68: The three primary elements of project management

Q69: A project consists of the following activities:<br>

Q70: Indirect costs always increase as a project's

Q71: What is a scope statement?

Q73: A project consists of the following four

Q74: A dummy variable is an activity inserted

Q75: In project management the term slack refers

Q76: A unique,one-time operational activity or effort is

Q77: The following table of probabilistic time estimates

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines