Multiple Choice
As part of its quality-improvement program a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element. The standard time for this job using an allowance factor of 16% is
A) 1.809 minutes.
B) 2.098 minutes.
C) 1.530 minutes.
D) 2.233 minutes.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: As part of a time study a
Q17: A work sampling study is being conducted
Q18: How many cycles should be used in
Q19: Determining the length of time it takes
Q20: The historical objective behind work measurements and
Q21: The allowance factor is a percentage increase
Q22: How many observations should be taken to
Q23: Management believes a critical piece of equipment
Q24: How many cycles should be used in
Q26: In a time study the standard time