Essay
A facility is trying to set up an assembly line,and has identified the various tasks,and their relationship to each other,as shown in the following table.They wish to produce 600 units per day,working two 8-hour shifts.
a.Draw a network diagram of precedence relationships.
b.Compute the required cycle time per unit in seconds.
c.Compute the minimum number of workstations required to produce 600 units per day.
d.Balance this line using longest processing time.
e.What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
(a)The precedence diagram appears below....View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: In assembly-line balancing, cycle time (the ratio
Q21: One guideline for determining the arrangement and
Q44: The _ is a non-numeric method for
Q54: Balancing low-cost storage with low-cost material handling
Q78: A manufacturing work cell has a takt
Q85: A facilities manager at a company headquarters
Q97: For which of the following operations would
Q121: _ layouts deal with low-volume, high-variety production
Q144: CRAFT is software for balancing assembly lines.
Q244: Explain how a load-distance model helps solve