Essay
A manufacturing work cell has a takt time of 7 minutes and is staffed by 10 workers. If the work cell delivers 68 units each day find
A. The total operation time
B. The amount of time worked during the day for all 10 workers combined
C. If the plant is open for only 8 hours per day, can the staff meet demand?
Correct Answer:

Verified
Total operation time = Workers required ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q35: What are the advantages of focused factories?
Q38: Four hundred and eighty minutes of production
Q73: A work cell is required to make
Q74: Briefly explain what "slotting" is. Why is
Q76: _ are fees manufacturers pay to get
Q79: A good layout requires determining<br>A) material handling
Q80: The concept of customizing in a warehouse
Q81: A work cell is required to make
Q197: _ refers to the physical surroundings in
Q224: A process-oriented layout is the traditional way