Multiple Choice
The project organization works best when which of the following conditions are satisfied?
A) Work can be defined with a specific goal and deadline.
B) The job is typical and familiar to the existing organization.
C) The work contains simple tasks requiring no special skills.
D) The project is temporary but unimportant to long-term organizational success.
E) The project is confined to one functional area.
Correct Answer:

Verified
Correct Answer:
Verified