    An Activity on a PERT Network Has These Time Estimates
Solved

An Activity on a PERT Network Has These Time Estimates

Question 94

Question 94

Multiple Choice

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is


A) 2.00.
B) 2.33.
C) 2.67.
D) 8.00.
E) 23.3.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q21: The phases of project management are:<br>A) planning,

Q86: Which of the following statements regarding PERT

Q89: The fundamental difference between PERT and CPM

Q90: A network consists of the following

Q91: Match the following steps in Microsoft's

Q93: Which of the following statements regarding Gantt

Q94: Identify and describe briefly each of the

Q97: Two critical path activities are candidates

Q110: Activity R on a CPM network has

Q116: A project being analyzed by PERT has

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines