Multiple Choice
A work center had actual input of 280 hours and actual output of 270 hours.What is the change in backlog?
A) 10
B) -10
C) 0
D) 1.037
E) Unable to determine with the given information
Correct Answer:

Verified
Correct Answer:
Verified