Multiple Choice
The critical path for the network activities shown below is ________ with duration ________.
A) A-B-D;10
B) A-B-E;11
C) C-E;12
D) A-D-E;13
E) A-B-C-D-E;22
Correct Answer:

Verified
Correct Answer:
Verified