Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?
Correct Answer:

Verified
(a)$2,000; (b)$4,000...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q13: If an activity whose normal duration is
Q14: Every network has at least one critical
Q20: The critical path for the network activities
Q56: Describe in words how to calculate a
Q61: Identify several advantages of using PERT (and
Q97: A project organization works best for an
Q107: The standard deviation of project duration is
Q113: _ is the amount of time an
Q118: A project organization that becomes permanent is
Q129: _ is decreasing activity time in a