Multiple Choice
A project being analyzed by PERT has 60 activities,13 of which are on the critical path.If the estimated time along the critical path is 214 days with a project variance of 100,what is the probability that the project will take 224 days or more to complete?
A) near zero
B) 0.0126
C) 0.1587
D) 0.8413
E) 2.14
Correct Answer:

Verified