    If an Activity Whose Normal Duration Is 13 Days Can
Solved

If an Activity Whose Normal Duration Is 13 Days Can

Question 13

Question 13

Multiple Choice

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,what is the crash cost per period?


A) $500
B) $1,500
C) $750
D) $13,000
E) $15,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Projects such as road building and plane

Q9: A contractor's project being analyzed by PERT

Q14: Every network has at least one critical

Q17: Three critical path activities are candidates for

Q66: Identify, in order, the six steps basic

Q107: The standard deviation of project duration is

Q113: _ is the amount of time an

Q118: A project organization that becomes permanent is

Q124: The _ is the computed longest time

Q129: _ is decreasing activity time in a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines