Lampost Manufacturing provides the following information: To produce a unit of product:
Mixing department 4 minutes per unit
Molding department 7 minutes per unit
Casting department 9 minutes per unit
Finishing department 5 minutes per unit
There is a wait time of 5 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 8 minutes.
Required:
a. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?
b. What is the bottleneck department?
c. What is the production rate? What is the cycle time of operation?
d. What would be the time to produce the first unit under a cellular manufacturing setup?
Correct Answer:

Verified
SUPPORTING CALCULATIONS:
a.
Process time...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
a.
Process time...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q35: Which of the following is true in
Q43: The document used by the lean control
Q105: In a lean environment, many overhead costs
Q108: Information about Taekwondo Corporation is as follows:
Q110: Information about Bodacious Corporation is as follows:
Q114: At the end of 2014, Diatomic Company
Q116: At the end of 2014, Diatomic Company
Q117: At the end of 2014, Diatomic Company
Q118: Information about Taekwondo Corporation is as follows:
Q137: Which of the following statements is true