Two Projects Have the Following NPVs and Standard Deviations A Person Who Selects Project a Over Project B Is
Multiple Choice
Two projects have the following NPVs and standard deviations: A person who selects project A over project B is
A) risk seeking.
B) risk indifferent.
C) risk averse.
D) None of the above