Essay
Project C has an expected value of $500 and a standard deviation of 50.Project D has an expected value of $300 and a standard deviation of 10.Comment on the desirability of these projects.
Correct Answer:

Verified
CVC = 50/500 = 0.10 CVD = 10/300 = 0.03 ...View Answer