There are two jobs to be assigned to two workers.The profit for worker A on job 1 is $5 and on job 2 is $8.The profit for worker B on job 1 is $10 and on job 2 is $12.How should the work be divided using the assignment method?
A) worker A assigned to job 1 and worker B assigned to job 2
B) worker A assigned to job 2 and worker B assigned to job 1
C) worker A gets both jobs 1 and 2
D) worker B gets both jobs 1 and 2
E) unable to determine
Correct Answer: