Essay
A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day.The tasks necessary to produce this product are detailed in the table below.
a.Draw the network described in the table.
b.Without regard to a production schedule,what is the minimum possible cycle time (in seconds)for this situation;what is the maximum?
c.What is the required cycle time (in seconds)in order to meet the schedule?
d.What is the theoretical minimum number of workstations needed to meet the schedule?
e.Balance this line using longest processing time.
f.What is the efficiency of the balance obtained in part e?
Correct Answer:

Verified
The network diagram appears below.Minimu...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q2: One of the major advantages of process-oriented
Q29: Which of the following is NOT one
Q54: What is the primary reason why retailers
Q81: Identify the seven fundamental layout strategies. Describe
Q82: Slotting fees:<br>A)are charged by retailers to stock
Q144: _ are charges that manufacturers pay to
Q218: Which of the following is one of
Q226: What is a servicescape? How is it
Q228: If a layout problem is solved by
Q269: The objective of layout strategy is to:<br>A)